Project Description
This project was for the construction of 7 new modular school buildings and associated hard and soft landscaped areas, including new fire access roads and parking area upgrades, at 7 Lower Schools in the Bedford area.
ACL works included the provision of Labour, Plant and Materials necessary to complete all substructure groundworks, drainage and service connections to the new modular buildings.
All sites utilised sustainable urban drainage systems which included installation of cellular attenuation tanks and Cell Web permeable parking systems.
New hard play areas and fire access roads were completed, including provision of all new macadam and white lining works
All works were completed on tight, live, school sites.
Architect
Lungfish - Scape Group
7th Floor City Gate East
Nottingham
NG1 5FS
T: 0115 9583200
Engineer
Diamond Wood & Shaw Ltd
The Old School
Blaby Rd
Enderby
LE19 4AR
T: 0116 2848989
Contract
Bedford School Projects
Client
Willmott Dixon Construction
Contract Period
36 Weeks
Value
£1,475,000